I am fairly new to MSP. Is it possible to have different work week schedules
for various tasks within one project? say certain tasks at 5days per week and
others at 6days per week?
If so, where do you set this up?
 
J

JulieS

Hello Al53,

The short answer is yes, you can have multiple calendars in Project.
You can create new base calendars or modify and existing base calendar
(Standard, 24 hours, Night Shift) through Tools > Change Working Time.

Base calendars can be used to schedule: an entire project (set in
Project > Project Information); serve as a task calendar (set on the
Advanced tab of the Task Information dialog box); or serve as a base
calendar for resources (set on the Resource Sheet).

I hope this helps. Let us know how you get along and feel free to
post back if you need more specific directions.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top