M
MaryS
We are using Project 2003 Professional and Server, and would like to
establish the following workflow for tasks:
1. Project Manager creates task and assigns to Resource Manager.
2. Resource Manager delegates task to appropriate and available Team Member.
3. Team Member accepts task, performs the work, and updates task to show %
complete or actual time.
4. Resource Manager is notified, reviews and either approves Team Member's
task update or rejects it.
5. If Resource Manager approves the update, Project Manager is notified for
review and approval.
We're having a problem setting up step 4 - Resource Manager approval. The
updated tasks are routing directly to the Project Manager for approval,
skipping the Resource Manager, and we want the RM to approve the work before
the PM confirms the update. We have the RBS set up to show the reporting
relationship between Resource Manager and Team Member. We do not want the
Resource Manager owning the tasks, so the 2 PM approach won't work. I can't
find any reference to this multiple approval process in any of the Project
documentation (2002 or 2003), or in the newsgroups (if it's somewhere, please
point me to it).
Is there some setting or some other process we can use to incorporate step 4
into our workflow? Or is this not an option right now?
Thanks for any help you can provide.
establish the following workflow for tasks:
1. Project Manager creates task and assigns to Resource Manager.
2. Resource Manager delegates task to appropriate and available Team Member.
3. Team Member accepts task, performs the work, and updates task to show %
complete or actual time.
4. Resource Manager is notified, reviews and either approves Team Member's
task update or rejects it.
5. If Resource Manager approves the update, Project Manager is notified for
review and approval.
We're having a problem setting up step 4 - Resource Manager approval. The
updated tasks are routing directly to the Project Manager for approval,
skipping the Resource Manager, and we want the RM to approve the work before
the PM confirms the update. We have the RBS set up to show the reporting
relationship between Resource Manager and Team Member. We do not want the
Resource Manager owning the tasks, so the 2 PM approach won't work. I can't
find any reference to this multiple approval process in any of the Project
documentation (2002 or 2003), or in the newsgroups (if it's somewhere, please
point me to it).
Is there some setting or some other process we can use to incorporate step 4
into our workflow? Or is this not an option right now?
Thanks for any help you can provide.