G
Greg Salts
Hi,
I would like to begin using Microsoft Project to manage schedules for a
number of resources. All rersouces use Outlook 2000 extensibly to track all
their appointments, meetings and events. I need to add all these events into
Project quickly to begin managing the project during the resources available
free time.
Is there a way to import an Outlook Calendar into Project as a resource
calendar?
I appreciate any help you can give on this question.
Thank You,
Greg
I would like to begin using Microsoft Project to manage schedules for a
number of resources. All rersouces use Outlook 2000 extensibly to track all
their appointments, meetings and events. I need to add all these events into
Project quickly to begin managing the project during the resources available
free time.
Is there a way to import an Outlook Calendar into Project as a resource
calendar?
I appreciate any help you can give on this question.
Thank You,
Greg