Can't change start date

T

Terri

Help! I can't change my start date on a particular task.
It isn't linked. It has a start date of 01/19/04, a
duration of 30 days, contraint is "As soon as possible".
There is nothing that I can change that will let me change
it from 01/19/04. Anyone know what's wrong?
 
W

William Raymond

Hi Terri,

How are you trying to change the start date of the project? You should be
doing this from the "Project->Project Information" window.

-Bill
 
T

Terri

No, I'm not trying to change the project start date, I'm
trying to change the start date of a task.
 
D

Dave White

Put a 0 in the Percent Complete field for the task even if it already has
one.

Dave
 
T

terri

I fixed it. It was contrained at a higher level.
-----Original Message-----
Hi Terri,

How are you trying to change the start date of the project? You should be
doing this from the "Project->Project Information" window.

-Bill
--
Bill Raymond
MS Project MVP
projectnation at hotmail dot com






.
 