Change Start - Finish times from dates to hours

T

Todd

I'm putting together a Disaster Recovery Plan when will be detailed in hours
and not dates
How can I can change the Start to show hours (start 6 hours from 0 hour) and
Finish Times (Finish 10 hours from 0 hour)

Also anybody know of any Enterprise Disaster Recovery Templates ; )
 
R

Reid McTaggart

You could create two custom number fields, each with a ProjDateDif formula
comparing the Start and finish dates to the Project Start date. The result
is in minutes, so divide by 60 in the formula.

-Reid
 
R

Rod Gill

Set the timescale to Hourly
Select Format, Timescale then you can change the time label from the hour to
Hour1, Hour 2 etc.

Under tools, Options you edit the date format to be time only if you wish.
 