Change the start date and move all tasks

J

Jack Pundick

I have a project with many tasks, some linked and some not. The project start
date has moved several weeks and I want to move all the task dates
accordingly. How do I do it.
 
R

regattagirl

Change the overall project start date. Choose Project, Project Information
and change your date.

Hope this is what you had in mind.

regattagirl
 
S

Steve House [Project MVP]

In Project 2002/2003 there is an "Adjust Dates" tool on the Analysis toolbar
that will adjust for a new start date. Unlike simply changing the start
date in the Project Information menu, it also will slip tasks that have
constraints so they occur at the same relative timeframe from the new start
date as they did with the original start date. In earlier versions of
Project you can find this tool as one of the stock supplied macros in the
Tools, Macro menu.
 