Jennifer
I am adapting a Project Professional plan that someone else created. Tasks,
durations and start/finish times were already entered, but resources were
not. I have now specified resources and working times. When I try to add
resource names to a task, however, it changes the start and/or finish date.
Even when I open the task information and delete the duration, adding a
resource alters the start/finish date. I have increased the resource's
working hours to 1000% just to see if that is what is causing the task dates
to change, but it doesn't help. Does anyone know what is going on, or what I
am doing wrong (or not doing)? Thx
durations and start/finish times were already entered, but resources were
not. I have now specified resources and working times. When I try to add
resource names to a task, however, it changes the start and/or finish date.
Even when I open the task information and delete the duration, adding a
resource alters the start/finish date. I have increased the resource's
working hours to 1000% just to see if that is what is causing the task dates
to change, but it doesn't help. Does anyone know what is going on, or what I
am doing wrong (or not doing)? Thx