B
bob1122
I have a project that was created with 6h work days. Also the tasks were
Fixed Units type. I want to change all tasks to Fixed Duration type (keeping
the same duration) and change to 8h work days. When I change to 8h work
days, the durations are reduced to 75% of the original values. Is there a
way to do this without changing each task individually? Thanks.
Fixed Units type. I want to change all tasks to Fixed Duration type (keeping
the same duration) and change to 8h work days. When I change to 8h work
days, the durations are reduced to 75% of the original values. Is there a
way to do this without changing each task individually? Thanks.