P
Pat Kelecy
I understand that Work = Effort (or Units) x Duration. So if one of these
is fixed, and a value is assigned to another, then the third can be uniquely
determined. Given this, I have the following questions:
1. What happens if the fixed quantity is changed? However does Project
recalculate the relation.
2. If a resource is not assigned, does Project assume a default value for
units?
Also, it seems more intuitive to make Work (number of man-hours required to
perform a task) the "scheduled" quantity, along with units, and let Project
compute duration, completion dates, etc. Then if you don't like how how
long things take, your only choice is to change units (add more resources or
work longer hours). I think this is the case for most work situations, but
for some reason most of the references I've looked at on MS Project assume
Duration is the scheduled quantity. Does anyone know what the rationale is
behind this?
Thanks for input. I appreciate it. -Pat
is fixed, and a value is assigned to another, then the third can be uniquely
determined. Given this, I have the following questions:
1. What happens if the fixed quantity is changed? However does Project
recalculate the relation.
2. If a resource is not assigned, does Project assume a default value for
units?
Also, it seems more intuitive to make Work (number of man-hours required to
perform a task) the "scheduled" quantity, along with units, and let Project
compute duration, completion dates, etc. Then if you don't like how how
long things take, your only choice is to change units (add more resources or
work longer hours). I think this is the case for most work situations, but
for some reason most of the references I've looked at on MS Project assume
Duration is the scheduled quantity. Does anyone know what the rationale is
behind this?
Thanks for input. I appreciate it. -Pat