M
MA
im trying to change the formula for the % complete or make a customized field
to calculate % complete of a project based on the number of completed tasks
in that project. For example
Task1
Subtask1
Subtask2
Task2
Subtask1
Subtask2
Now given a format like that I ud like % complete to compute so that each
task contitutes of the total percentage in the project, in this case Task1 +
Task2 = 100, so if task one is complete the project shud stand at 50% so that
if there is any change in the time taken for the particular task the total
percentage complete is not affected.
Tha Subtasks shud be a part of the Tasks and the percentage of the Tasks
completed shud be calculated from the Subtasks completion. So that if
Subtask1 is complete then Task1 should stand at 50 percent.
I hope its clear what Im trying to accomplish. Any suggestions as to how i
might go abt doing this will be highly appreciated. I have to solve this in 3
days time and i must add that Im a novice at using this software.
Thanks in advance.
to calculate % complete of a project based on the number of completed tasks
in that project. For example
Task1
Subtask1
Subtask2
Task2
Subtask1
Subtask2
Now given a format like that I ud like % complete to compute so that each
task contitutes of the total percentage in the project, in this case Task1 +
Task2 = 100, so if task one is complete the project shud stand at 50% so that
if there is any change in the time taken for the particular task the total
percentage complete is not affected.
Tha Subtasks shud be a part of the Tasks and the percentage of the Tasks
completed shud be calculated from the Subtasks completion. So that if
Subtask1 is complete then Task1 should stand at 50 percent.
I hope its clear what Im trying to accomplish. Any suggestions as to how i
might go abt doing this will be highly appreciated. I have to solve this in 3
days time and i must add that Im a novice at using this software.
Thanks in advance.