Nope - baselines don't figure into completion percentages at all,
regardless of whether you're measuring % Complete, % Work Complete, or %
Physical Complete. You are correct, though, that durations are a dynamic
thing. I like to think of the plan as displaying two types of info once
work has begun ... historical fact about what has transpired up to the
status date and projected performance of what has not yet been done based
on projections derived from how things have gone so far. The baseline
preserves our original estimates. As an example, we have done 3 days on
a task and the resource doing the work estimates that he will take 9 more
days to complete it. We are 25% Complete on that task ... period. It's
irrelevant whether our original estimate was 2 days, 12 days, 20 days, or
200 days. As we began work and saw how things were progressing we've
learned that it will probably take 12 days and we've done 3 of them, that
task is 25% Complete because we're 25% of the way along the time from when
we started until we can holler "done!" and walk away from it. To see how
that compares to our original estimates we need to switch over to a metric
called 'earned value' that compares essentially man-hours of work that
have been done (current plan's actuals) to the man-hours that were
supposed to have been done (baseline plan's scheduled) up to the status
date, expressed in units of cost, which is sometimes a hard concept to
wrap one's head around.
From a practical standpoint, don't even ask your resources for an update
phrased as "% Complete" - you have no idea what is in their mind when they
say "I'm 30% complete." Instead, ask them how much time they've put in
on it so far and how much more time do they think it will take before
they're done. There's your actual duration and remaining duration and
Project will calculate the new total duration and % completion for you
when you enter them. There's a natural human tendency to over-estimate
one's progress in order to look good in the boss's eyes and odds are that
as soon as they take a first look at the task the resource will report
they're 75% done. Pinning them down to "how much have you done and how
much is left to go" goes a long ways in minimizing that effect.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Diver512 said:
So conceptually, are we tracking this project improperly? Groups seem to
be
giving us Physical % Completes rather than actual % Completes against the
duration. Basically the problem is that the original duration estimates
given in the plan do not hold true. What development project ever has
duration estimates that hold true throughout? How do we show whether we
are
ahead or behind schedule when everything is being measured against
constant
durations?
Ok correct me if I'm wrong. You update actual duration percent completes
as
you feel how far along you are. The durations will actually recalculate
according to that entered percentage. The recalculated durations can
then be
measured against the baseline to see if the tasks/project are on
schedule.
Sound right? And this is why I asked where I should take an MS Project
Course in my first post.
Thanks again. You guys are MVPs.
Brian
Steve House said:
You could use % Physical Complete if you want to update based on what %
of
the task the developers think is done but be aware that % Physical
Complete
does not rollup from the detail lines. "% Complete" is by definition
(ActualDuration/TotalDuration) * 100 and that cannot be altered any more
that the definition of "White" can be altered to mean "the complete
absence
of light." Other ways of tracking progress may be useful but anything
other
than comparing duration completed versus total to be done can't properly
be
called "% Complete." For a summary task, the rolled up % Complete is a
little more complicated. There it is a weighted value computed as the
sum
of the actual durations of all the subtasks divided by the sum of the
total
durations of all the subtasks.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi,
So I have a large project with numerous major sections. The top
section,
which we will call "Development" is beginning to be populated with
percent
completes and actual start/finish dates. We are updating these every
week.
As some tasks are changed in other sections of the plan, percent
completes,
durations, and finish dates are shifting in the Development section.
One
day
Development will be 60% complete and the next day it will all of a
sudden
be
51% because the tasks in this section are moving around when people
edit
other unrelated sections. We would like to be able to update the
tasks
with
the percentage the developers think it is complete without this
unexplained
shift, and not as a percent of the duration complete.