T
tommcbrny
Hello,
If a project resource completes a task earlier than expected, is it possible
to automatically accelerate the start dates on dependent tasks by marking the
completed task as 100% complete?
This does not happen in my current project plan. For example, task 25 has a
finish date of Friday, 5/5 but is actually completed on Thursday, 5/4. Task
27 is dependent on task 25 and thus has a start date of Monday, 5/8 because
of 25's original finish date.
I would expect that marking 25 as 100% would move the finish date for 25,
resulting in the start date for 27 to move up as well.
Both Task 25 & Task 27 have constraint type ASAP, no constraint date, Task
type is Fixed Units, Effort Driven is checked, Earned value method is %
complete.
Any way to do this besides manually moving up the finish dates when tasks
are completed early?
Thanks!
Tom
If a project resource completes a task earlier than expected, is it possible
to automatically accelerate the start dates on dependent tasks by marking the
completed task as 100% complete?
This does not happen in my current project plan. For example, task 25 has a
finish date of Friday, 5/5 but is actually completed on Thursday, 5/4. Task
27 is dependent on task 25 and thus has a start date of Monday, 5/8 because
of 25's original finish date.
I would expect that marking 25 as 100% would move the finish date for 25,
resulting in the start date for 27 to move up as well.
Both Task 25 & Task 27 have constraint type ASAP, no constraint date, Task
type is Fixed Units, Effort Driven is checked, Earned value method is %
complete.
Any way to do this besides manually moving up the finish dates when tasks
are completed early?
Thanks!
Tom