Hi All!
May I ask a Friday afternoon question please?
Question: Why is the Completed Through date as displayed in the progress
lines on my gantt charts a date in the future? In my case, many of my tasks
show a completed through date of 08/01/07, though I have work scheduled
between now (07/20) and 08/01 and I have no actual work in those dates.
I finished updating my project plans. (We use Project Server 2003, but this
question is about Project Pro 2003.) I accepted my updates from the server.
Hit cancel so the updated tasks remained marked. Then used the update
project dialog box to reschedule uncompleted work after today's date
(07/20/07) for selected tasks only. Project dutifully moved the tasks out
(mostly out, sigh). However, I have noticed for the past few weeks that the
completed through dates and progress lines on my gantt charts (tracking and
regular) show the most of the tasks as being completed through a future date
(08/01). Even though I have work scheduled for days between then and now
and have no actual work between then and now.
I have tried to provide all relevant information, but if anything further is
required, please let me know and I will provide it.
MS Project Pro 2003 SP2a
Project Server 2003 SP2 - if it matters
I'm so confused!
Crook
May I ask a Friday afternoon question please?
Question: Why is the Completed Through date as displayed in the progress
lines on my gantt charts a date in the future? In my case, many of my tasks
show a completed through date of 08/01/07, though I have work scheduled
between now (07/20) and 08/01 and I have no actual work in those dates.
I finished updating my project plans. (We use Project Server 2003, but this
question is about Project Pro 2003.) I accepted my updates from the server.
Hit cancel so the updated tasks remained marked. Then used the update
project dialog box to reschedule uncompleted work after today's date
(07/20/07) for selected tasks only. Project dutifully moved the tasks out
(mostly out, sigh). However, I have noticed for the past few weeks that the
completed through dates and progress lines on my gantt charts (tracking and
regular) show the most of the tasks as being completed through a future date
(08/01). Even though I have work scheduled for days between then and now
and have no actual work between then and now.
I have tried to provide all relevant information, but if anything further is
required, please let me know and I will provide it.
MS Project Pro 2003 SP2a
Project Server 2003 SP2 - if it matters
I'm so confused!
Crook