% Complete

V

verossa

Here is my work sheet:

ID Resource Name Units Work Baseline
Act.Work Rem.Work
1 Proj Mgmt 0.25 8h 4h
0h 8h
2 Prog Mgmt 0.63 21h 15h
0h 21h

1) Populated the tasks in the resource work window below the gantt chart
(split screen)
2) Updated the tasks in the tasks usage to show an increase from the
baseline and to ensure durations did not change (as per previous post)

Question:
3) Rem. Work (does this "remaining work") in the resource work view is still
8h / 21h respectively. How or where do I input the actual physical hours
done. When I inputed the data in the Task Usage I assumed this is what I
was doing - but as there are still Rem. Work I must be incorrect. I have a
feeling I am getting confused what screens are executing which task.

Having updated the Task Usage sheet with over-runs (more hrs than scheduled)
I expected to see the '% Complete' bar activated on the Gantt Chart. I am
assuming the Task Usage is another plan of task as opposed to the executed
time on tasks.

Thanks in advance to all whom respond.

Smiles - Vers
 
V

verossa

Please discard this post:

If you are interested Gerard has answered this in my previous post: "Actual
work altering task durations".

Thanks again Gerard - Vers
 
G

Gérard Ducouret

You are welcome , Vers

Gérard

verossa said:
Please discard this post:

If you are interested Gerard has answered this in my previous post: "Actual
work altering task durations".

Thanks again Gerard - Vers
 