M
melmer
Hi there....I have a question regarding the % Complete column. I know
this is asking alot from Project, but is there any way at all to force
the % over 100 when the Actual Work exceeds the Baseline Work? Also,
is there a way to show the work numbers in red once they go over the
baseline value?
These forums have already proved to be very helpful - thank you for
sharing your expertise!
Martie
this is asking alot from Project, but is there any way at all to force
the % over 100 when the Actual Work exceeds the Baseline Work? Also,
is there a way to show the work numbers in red once they go over the
baseline value?
These forums have already proved to be very helpful - thank you for
sharing your expertise!
Martie