D
Diogo Tortajada
I need to create the percentage of conclusion for the activities based on the
dates of beginning [Baseline Start] and end [Baseline Finish] of the base
line, however the project only manages to update the percentage based on the
beginning [Start] and ended [Finish] dates of the normal project. Some ideia??
dates of beginning [Baseline Start] and end [Baseline Finish] of the base
line, however the project only manages to update the percentage based on the
beginning [Start] and ended [Finish] dates of the normal project. Some ideia??