As you describe it here, your "end date" is not the end date. What you are
calling the end date is probably the cutover date to the converted whatever
towards the end of your project and that is likely an important milestone
with a deadline on it, but the actual project "end date" is DEFINED as the
date when the absolutely last little bit of work on the very last task, is
completed and everyone goes home never to work on any part of the project
again. With MS Project (and CPM scheduling in general) you can never, ever
fix BOTH the project start and project end dates. You have to pick one or
the other to set and then it's the software's function to calculate the
other date for you along with the shortest schedule that will achieve it.
Along that pathway you'll have, as I said, a milestone that represents what
you're presently calling the end date. Set the start of the process with
the Project Start date in the Project Information dialog. Set the required
competion ne cutover by using the Deadline field on the advanced tab of the
Task Information dialog for the milestone. Note that the date shown for the
milestone will be the calculated date that Project concludes it will be able
to take place IF the work leading up to it is organized the way you have
input it. If it calculates it to be after the required deadline, you can't
just wave a magic wand and set it to the required date - you have to
actually reorganize the work leading up to it so Project's calculated date
will pull forward to lie on or before the required deadline date. The idea
of the plan is not just to document the requirements and your intentions -
it's to provide you with a dynamic model of the project that you can use to
do "what-if" kinds of analysis in order to predict the probable impact of
the management and deployment decisions you make, ultimately allowing you to
create a plan that has a higher probability of meeting your business
objectives than you'd get flying by the seat of your pants.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
sb said:
We work with conversions and can take 30, 45, 90 days to complete a
conversion. How do I setup the project plan template to adjust for
different
end dates? However, we have tasks that start and finish prior and after
the
conversion end date. The start and finish dates are setup within the lag
field.