Mike

I have used the Baseline and Baseline 1 fields in my schedule. However,
there is only a cost spread for the regular work and baseline work.



Any explanation as to why there is not a spread for the baseline 1 work?
 
R

Redneck David

Mike,

That can be done. Here's how:

1)Right click in the right hand part of the vew (yellow)
2)Select detail styles
3)In the available fields select your Baseline 1 field and make it available

From there its easy.
 
J

JulieS

Mike,

What version (including Service pack) of Project are you using? With
Project 2003 SP-3 I see both Work, Cost, Baseline Cost, Baseline Work
and Baseline1 Cost and Baseline1 work in the Task Usage view. Are you
using Cost resources or work resources with costs?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
M

Mike

thanks for the reply dave but i already have the field available, it is just
that there are no values showing for it.
 
M

Mike

Hi Julie

I am running 2 versions on one laptop. the schedule i am dealing with here
is in MS project 2007 with SP1 MSO.

Using work resources with cost.

Thanks
 