Hello

I use Project Server 2007 ->
Project Managment: Ms Project 2007
Resource: Project Web Access


I want to create a Team A (no a generic resource, no create a build
team enterprise i know selected the pool resource).

This Team A is associated with 3 resources: R1, R2 and R3. The
resources I select of enterprise pool.

And when I asisgn a task to the Team A it means whatever of this 3
resources can make this task. Then R1 or R2 or R3 can input hours to
this task

is it possible?

Thank in advance

mbg
 
M

Mike Glen Project MVP

Hi mpg,

I suggest you post on the Microsoft.public.project.server newsgroup where
the experts hang out.

Mike Glen
Project MVP
 
D

Dale Howard [MVP]

mdg --

In the future, please post your Project Server 2007 questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
yes, you CAN create team resources in Project Server 2007. Refer to the
following FAQ for the steps your Project Server administrator must perform
to create Team resources:

http://www.projectserverexperts.com/Shared Documents/CreateTeamResource.htm

Hope this helps.
 