G
Glen
I am currently using MS Project Professional 2002 and MS Project Server 2002, I am trying to create a time sheet system for the company. I have created a project and within that project I have created 15 or so tasks, and assigned people to each of those tasks. In the start column I put 12/1 and in the finish field I have 12/31/10 so the duration is around 1800 days. I publish the project out to the server and everyone is able to access their tasks.
My questions
1). How do I create a report that shows how much time has been spent on a particular task
2). How do I get it so that it doesn't automatically put hours in each task for everyone, I want the employees to do this
Any advice on how to build a timesheet system using MS Project Pro 2002 and MS Project Server 2002 would be greatly appreciated
Thanks in advance !!
My questions
1). How do I create a report that shows how much time has been spent on a particular task
2). How do I get it so that it doesn't automatically put hours in each task for everyone, I want the employees to do this
Any advice on how to build a timesheet system using MS Project Pro 2002 and MS Project Server 2002 would be greatly appreciated
Thanks in advance !!