Custom EV

B

bauer172uw

Our organization uses MS Projec Server 2003 along with Project Professional
2003. We are using the Physical % Complete (user defined) field to calculate
our Earned Value. We wish to use a credit/no credit method for this. For
example, tasks < 100% Complete should take no earned value credit (also it
should not count against them, especially for SPI). Only for tasks 100%
complete do we want to effect our EV.

So far we have created a macro to accomplish this but we are still having
difficulties. Does anyone know of a way in project to automatically do this?
I have heard that this was simply a check box in older project versions.

Thanks for any help!
Mike
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top