Custom View/Filter - Please Help!

C

charlesdlm

--------------------------------------------------------------------------------

Hi,

Really hoping someone can help me with this because I have been looking for
answer without any success so far.

I have a large project where all my task dependancies are finish - start.
(Obviously some tasks have no dependacies at all).

I want to see what tasks my project resources can work on presently. This
does not necessarily = all open tasks as I dont want to see tasks which they
cant work on due to the fact that there are related predecessors/dependancies
still open.

To summarise I would like to see (using a filter or VBA)

1. All open tasks without any predecessors &
2. All open tasks with related predecessors/dependancies that are themselves
completed. Ie if task 5 as a predecessor of task 4 (finish start) and task 4
is 100% completed then I would like to see task 5. But if task 4 has only 80%
then I dont want to see task 5 (as task 5 cant be started yet).

Update:
My understanding is that this cant be done via a filter but that VBA will be
required :-(

Eagerly awaiting your responses - Regards Charles
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top