W
wjaramillo
I have an existing task with sub tasks. How can I have the main task not
register in the duration? For example, the main tasks has 10 subtasks with a
duration totaling 49 days. The main tasks may start concurrently with another
task. However, the default needs to be that none of the subtasks should start
until the criteria is met. The parent task is showing 99 days and part of
that are the 49 days. I need to keep the 49 days subtasks visible. And they
can not count towards my 99 days. Therefore my parent should show 50 days
instead of 99 days. Then if the critieria is met I can enable the 49 days to
be added and total up to 99 days.
register in the duration? For example, the main tasks has 10 subtasks with a
duration totaling 49 days. The main tasks may start concurrently with another
task. However, the default needs to be that none of the subtasks should start
until the criteria is met. The parent task is showing 99 days and part of
that are the 49 days. I need to keep the 49 days subtasks visible. And they
can not count towards my 99 days. Therefore my parent should show 50 days
instead of 99 days. Then if the critieria is met I can enable the 49 days to
be added and total up to 99 days.