PattiTechWriter said:
Hi John! I think I'm making this harder than it has to be. I went into the
Customize Fields screen and changed the values of the 20 flags to Yes. (Yes,
I have multiple resources on multiple tasks). But then I'm lost.
In the Resource Sheet, it shows all 20 custom fields under each resource
name and then in the Gantt view, no fields show.
If you have time, can you walk me thru this? I'm getting frustrated with my
inability to figure out what is probably an easy puzzle.
Thanks,
Patti
Patti,
I'm sorry, I was not very clear and Project is one of those applications
that can get very confusing in a hurry. I mentioned setting up spare
flags for each resource and it would be natural to assume that should be
done on the Resource Sheet. However that is not what I meant and it is
complicated by the fact that Project has three database parts - one for
tasks, one for resources, and one for assignments. Each of the three
have spare fields for text, number, flags, etc., but Task Flag1 is not
the same as Resource Flag1 nor is it the same as Assignment Flag1 - they
are all independent. And to make it even more interesting, some views
(e.g. Resource Usage and Task Usage) can be made to show a spare field
(e.g. Flag1) but the flag field is different depending on whether you
are looking at a Resource row, a Task row or an Assignment row.
Ok, that's the lesson for today. Now to be more clear with my suggestion.
1. On the Gantt View display as many spare flag fields as you have
resources (hopefully you have 20 or less or this method won't work for
you). For example if you have 10 resources, set up columns on the Gantt
View to show 10 spare flag fields. (Note: it will be helpful to also
display the Resource Names field immediately to the left of the flag
fields)
2. For each task, take a look at the resources assigned and put a "yes"
in each flag field you have designated for those resources. For example,
if Joe and Mary are assigned to a task and you have represented them by
Flag1 and Flag4, then put a "yes" in each of those flag fields.
3. Then sort by Start date. Be sure to uncheck the box to keep the
outline structure at the bottom of the Sort window.
4. Finally, to get a report for Joe, set up a filter for Flag1.
Similarly filtering on Flag4 will get a report for Mary (at least in my
example). Note: to make filtering easier you could set up an interactive
filter that will ask you which flag to filter on. You do that by simply
entering "Enter Flag Field number"? in the Value column in the Filter
window. Note the question mark must be after the quote.
Hopefully this is more clear, and, it will get you what you need.
John
Project MVP