Hi
You could get the required report by the following method:
In the 'Resource usage' view use the filter 'Resource range'. By default the
filter only shows a Resource name and its total assignment for each day. To
view individual assignments of each activity under it edit the filter. While
editing, retain the first selection and in the second selection row with
Field name 'Assignment' change the Value from 'No' to selection
'[Assignment]'. Now when you apply this filter you will get the total and
individual task assignment for each resource of your selection for each day.
Like this you may take the printout for each resource separately.
There is a 'Resource usage' report in 'workload' group. There also for each
Resource separately you may apply this Filter. But, the filter can't be
edited in that view.
I hope it helps.
Vanita
--
Project Management consultant and trainer
(e-mail address removed)
Chicago2Paris said:
I'm looking for a report that will show which resource does which task at
what time. The default report is useless and I can't seem to figure how to
customize it for my needs. I only want to show one resource per report that
indicates their upcoming tasks starting at a certain date. Using MSP 2003
Pro. Thanks.