Dates are doubled of Duration

B

borgel

For some reason this new project schedule that I've just started is doubling
the dates of every duration of every task, e.g. the duration is 1 day, the
start and end dates are 2 days apart, etc. I'm using the Standard calendar
template and checked to make sure that the working times are correct and
there are not a bunch of holidays marked for any reason - it's just a
standard calendar. What else can I check?
 
G

Gérard Ducouret

Hi borgel,

Display the time beside the dates : Tools / Options / View / Date format...
something with 12:33.
Then check all the dates and time. Check the consistency between the
settings in Tools / Options / Calendar and the calendar slots of time

Hope this helps,

Gérard Ducouret
 
B

borgel

I figured it out myself..... somehow or another the Project Calendar options
had changed to say 24 hours in a day, not 8.0. Once I changed that, I was
fine (except that my durations then tripled and I had to change them back).
 