In MPP 03, when I enter a 2 day duration for an activity with a start
date of 2/23 - the end date populates with 2/25, which is a
Saturday. What may be causing this? I have checked my standard
calendar and it states saturday and sunday are 'non -working'. Thx.
 
J

John

In MPP 03, when I enter a 2 day duration for an activity with a start
date of 2/23 - the end date populates with 2/25, which is a
Saturday. What may be causing this? I have checked my standard
calendar and it states saturday and sunday are 'non -working'. Thx.

bpomykala,
How about your resources? Do the resources assigned to the task also use
the standard project calendar or does their calendar say they can work
on weekends? To check this, go to the Resource Sheet and select a
resource. Then go to Tools/Change Working Time.

John
Project MVP
 