J
James G
Hi Gang!
I'm a bit stuck on this one, so hopefully someone has encountered this and
has some tips on its resolution:
Using MSP 2000 with Project Central. Programme with appx. 600 lines. Nothing
special in terms of set-up or configuration.
Problem: When inserting a new task, as part of a sub-set, the start-date of
the new task seems to be governed by the start-date of the task that is
immediately above, even though the task above has absolutely no relationship
with the new task. Regardless of how I try and link the task, I can never get
it to start earlier....although I can get it to start later. I think I've
checked-out most of the optional defaults etc. but nothing seems to change
it. It's happening only with this file (which I inherited).
Any got any ideas.
Thanks indeed.
James.G
I'm a bit stuck on this one, so hopefully someone has encountered this and
has some tips on its resolution:
Using MSP 2000 with Project Central. Programme with appx. 600 lines. Nothing
special in terms of set-up or configuration.
Problem: When inserting a new task, as part of a sub-set, the start-date of
the new task seems to be governed by the start-date of the task that is
immediately above, even though the task above has absolutely no relationship
with the new task. Regardless of how I try and link the task, I can never get
it to start earlier....although I can get it to start later. I think I've
checked-out most of the optional defaults etc. but nothing seems to change
it. It's happening only with this file (which I inherited).
Any got any ideas.
Thanks indeed.
James.G