Dear all,
why are there differences between scheduled work in task and resource
view within the project client?
This occurs when I try to compare work variance (work MINUS scheduled
work) in the task view (e.g. GANTT) and within the resource view! The
values are different!
Before that I have saved a baseline and added some tasks (without
resources --> no work!!!) and did not update the baseline. Somehow I
now see these differences...other values for scheduled work in resource
view than in task view!?!??!?
Thanks,
Thomas
why are there differences between scheduled work in task and resource
view within the project client?
This occurs when I try to compare work variance (work MINUS scheduled
work) in the task view (e.g. GANTT) and within the resource view! The
values are different!
Before that I have saved a baseline and added some tasks (without
resources --> no work!!!) and did not update the baseline. Somehow I
now see these differences...other values for scheduled work in resource
view than in task view!?!??!?
Thanks,
Thomas