Display time differently

P

pmack

In a Gantt chart, how do I display tasks in the schedule that are complete differently than tasks that are not complete? (For example, I want solid lines/milestones for completed tasks, and outlined lines/milestones for tasks that are not complete.) Thanks!
 
J

John

Pmack,
Set up separate barstyles for finished and unfinished tasks. Go to
Format/Barstyles and either modify one of the default bars and milestone
indicators or create new ones. In the column that says "show
for...tasks" use the list in the selection box to select "finished" and
"not finished" as appropriate.

Hope this helps.
John
 
J

Jan De Messemaeker

Hi,

Use the list separator (depending on the settings, a comma or a ;)
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
pmack said:
In the column that says "show for...tasks", can I select more than one
option? I've tried using the Ctrl key but it doesn't work. I am trying to
choose Milestone and finished...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top