That's the way material resources are tracked. Create a resource "Coal" as
a material resource, material label "pounds." Create a task X. In the
Window menu choose "split" to split the screen With task X selected, assign
the resource coal, set the units to "50/day" and the work to "600" and
you'll find it calculates the duration to be 12 days. Be very very careful
with this, though, because if you assign a work resource as well, the work
resources will over-ride the duration calculated by the usage of the
material resource - in my example if you add resource Bill at 100%
everything with be fine at first BUT if you then try to change the total
coal to be used to 1000 pounds you'll find the duration number doesn't
change but the elasped time shown by the Gantt bar does! It's as if Bill's
work governs the duration numbers but the usage of coal governs the elapsed
time! I'd strongly suggest manually estimating the duration rather than
asking Project to do it for you to avoid those sorts of problems.