Hi hope someone can advise
I have just inherited a plan (500 lines) which has a duration set in days
for 33+ resources. My new PM has asked me how many hrs do i need to complete
the project
Historically -
Resources have been providing guesstimate information for their tasks
durations saying "thats going to take about 3 weeks" so the project has been
allocating 100% for the period.
Now - the project is tight for time/money so I have asked each resource how
long they actually need and there duration - so I have ended up now with say
" i only need 6 hrs over a different 3 weeks period"
The question is : how do i incorporate this new info into the plan bearing
in mind that some acitivities have already started and, i need to be able to
give a accurate requirment to my PM.
thanks in anticipation
I have just inherited a plan (500 lines) which has a duration set in days
for 33+ resources. My new PM has asked me how many hrs do i need to complete
the project
Historically -
Resources have been providing guesstimate information for their tasks
durations saying "thats going to take about 3 weeks" so the project has been
allocating 100% for the period.
Now - the project is tight for time/money so I have asked each resource how
long they actually need and there duration - so I have ended up now with say
" i only need 6 hrs over a different 3 weeks period"
The question is : how do i incorporate this new info into the plan bearing
in mind that some acitivities have already started and, i need to be able to
give a accurate requirment to my PM.
thanks in anticipation