B
Bonnie
Using Project 2007. Project is taking the task, with the longest duration,
and summarizing it as the entire duration for that set of tasks. The total
days should add up to 4 days for the 'construction'. Example of problem
below:
Construction 2 days (this is the summary)
1. Install dura rock 1 day
2. Set tile 2 days
3. Grout tile 1 day
I've been using the MS Project Step by Step book and may have changed some
default for calculation that I was not aware of as well.
and summarizing it as the entire duration for that set of tasks. The total
days should add up to 4 days for the 'construction'. Example of problem
below:
Construction 2 days (this is the summary)
1. Install dura rock 1 day
2. Set tile 2 days
3. Grout tile 1 day
I've been using the MS Project Step by Step book and may have changed some
default for calculation that I was not aware of as well.