Let's say we have a task "Primp Hairdo." Primping can be of two types:
(1) It takes a fixed duration of 8 hours and must start/finish on the same
day (otherwise you get the bedhead thing going). Doing it the way I
suggested above is about the only way to make it happen starting and stopping
the same day.
(2) Primp Hairdo can take a variable amount of time and is used to fill in
the remainder of a day. So, if all the predecessors finish at 11AM, I primp
until 5PM (6 hours), if all the predecessors finish at 4PM, I can only primp
for 1 hour. To do this will require some special coding to dyanamically
determine the amount of time to assign to Primping. Welcome to the world of
VBA; the solution is not readily presented here -- it would take some work.
It depends on how soon after all the predecessors complete that I must start
my successor activity. For us, we have a rule that our customer must be
notified in advance of any test. So, we only conduct tests on Tueday,
Wednesday or Thursday allowing the customer to travel on Monday or Friday.
(The tests take 1 day). So, we have to notify them on Thurday of our intent
to test on Tuesday. We combine this will a lag time and the procedure
outlined above to get the desired start dates.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project