B
ben.poitras
I have some tasks that occur before the project start date, and some
that extend after the project end date.
This is acceptable, but I want to generate a critical path that
excludes these tasks, and defines the critical path excluding these
tasks.
Is there a way I can do this?
Thank you in advance!
Ben.
that extend after the project end date.
This is acceptable, but I want to generate a critical path that
excludes these tasks, and defines the critical path excluding these
tasks.
Is there a way I can do this?
Thank you in advance!
Ben.