J
JPD
Task A is the predecessor to Task B, the relationship is Finish to
Finish.
Both task A & B have started. If I change the finish date on task
A ... the finish date on task B change should change?
It does not seem to be working for me...
any help appreciated.
Thanks,
J
Finish.
Both task A & B have started. If I change the finish date on task
A ... the finish date on task B change should change?
It does not seem to be working for me...
any help appreciated.
Thanks,
J