Check the calendar for the project, and if a different calendar has been
assigned to specific tasks (Tools > Change Working Time, Project > Project
Information, and the Task Calendar column respectively).
Check the resources assigned to the tasks to confirm they have the right
calendar assigned (in the Resource Sheet)
Check Format > Layout to confirm the bar splits are displayed.
Right click on the Chart, select Nonworking time, and confirm that the settings
there are not causing it to appear like work is happening on the weekends.
Confirm that duration is not in elapsed days "ed," but in days "d".
That's all I could think of off of the top of my head. Let me know if none
of those work.
- Andrew Lavinsky
Blog:
http://blogs.catapultsystems.com/epm