J
Jeff H
Is there a way to make Project recalculate the finish date based upon percent
complete? If I assume it takes 100 days to complete a task, I should be 33%
complete at day 33. But what if I am actually 50% complete at day 33? Can
project forcast a revised completion date of 66 days? I think I am asking
the program to compare work complete vs. actual time incurred. If there is a
way to do this it would be very helpful to me in my project tracking.
I need to keep this very simple, as I am only interested in total duraton
for several buildings we are developing, and I need an easy way to see if the
building is running ahead or behind our scheduled delivery date. We do not
schedule resources and are simply looking for a tool to help us understand
where we are at any given point of time.
complete? If I assume it takes 100 days to complete a task, I should be 33%
complete at day 33. But what if I am actually 50% complete at day 33? Can
project forcast a revised completion date of 66 days? I think I am asking
the program to compare work complete vs. actual time incurred. If there is a
way to do this it would be very helpful to me in my project tracking.
I need to keep this very simple, as I am only interested in total duraton
for several buildings we are developing, and I need an easy way to see if the
building is running ahead or behind our scheduled delivery date. We do not
schedule resources and are simply looking for a tool to help us understand
where we are at any given point of time.