M
Marc
I have limited experience is creating formula's in MS Project. The only one I
use is a Performance Ratio Formula which is IIf([% Work Complete]=100,[Actual
Work]/[Baseline Work],0)... in any event, i have been trying to create three
new formulas which 'should' be easy but I just can't figure it out. Here is
what I want:
Create a new field with a formula that will show me if the task is estimated
to begin (Baseline Start) sometime this week (Monday through Friday).
Create a new field with a formula that will show me if the task is estimated
to finish (Baseline Finish) sometime this week (Monday through Friday).
Some sort of formula that will show me which tasks need to be updated. For
example, if '% Complete' is '0' and the Start Date is less than today's date.
Any guidance or assistance will be greatly appreciated!
use is a Performance Ratio Formula which is IIf([% Work Complete]=100,[Actual
Work]/[Baseline Work],0)... in any event, i have been trying to create three
new formulas which 'should' be easy but I just can't figure it out. Here is
what I want:
Create a new field with a formula that will show me if the task is estimated
to begin (Baseline Start) sometime this week (Monday through Friday).
Create a new field with a formula that will show me if the task is estimated
to finish (Baseline Finish) sometime this week (Monday through Friday).
Some sort of formula that will show me which tasks need to be updated. For
example, if '% Complete' is '0' and the Start Date is less than today's date.
Any guidance or assistance will be greatly appreciated!