I opened up my resource pool as read/write (the middle option of the three)
to assign a different base calendar to some resources. I made my changes,
saved and closed the resource pool. Later I opened the resource pool again,
as read/write and found that my changes didn't take!
I assume MS Project would alert me if someone else were in the resource
pool. I'm wondering what could be causing this? I went in again and made a
different type of change (sorted by name), saved and closed it again. I
opened it back up and again the changes were lost.
I have SP2 installed.
Any ideas? Thanks!
to assign a different base calendar to some resources. I made my changes,
saved and closed the resource pool. Later I opened the resource pool again,
as read/write and found that my changes didn't take!
I assume MS Project would alert me if someone else were in the resource
pool. I'm wondering what could be causing this? I went in again and made a
different type of change (sorted by name), saved and closed it again. I
opened it back up and again the changes were lost.
I have SP2 installed.
Any ideas? Thanks!