Hide completed sub-tasks?

A

andy

project v2003 pro
Is there a way to hide WBS sub-tasks that are marked as
complete, leaving the task (main entry), and any sub-tasks
not yet marked as being 100% complete?

Thanks in advance
 
J

Jan De Messemaeker

Hi,

Look for the little window saying "All Tasks", select "Incomplete Tasks"
Or Project, Filtered for.... select incomlete tasks.
HTH
 
A

andy

Greetings Jan,
Thank God that you and others are willing to share their
expertise! Your advice worked exactly as I had hoped, and
I greatly appreciate your help. Thank you.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top