D
Dammika
Example : A task with 40hr Duration started 2 days ago but the engineer has
completed 80% of the task during the 2 days. I need to make my project plan
end date to change based on the % complete to complete this task on the 3rd
day.
Can this be done? I tried many options and non worked.
completed 80% of the task during the 2 days. I need to make my project plan
end date to change based on the % complete to complete this task on the 3rd
day.
Can this be done? I tried many options and non worked.