How do I distribute specific hours to multiple tasks?

B

Byron9261

I have a series of parallel tasks that I want one resource to work. I want
to keep the total duration but spread the hours. In other words I have 4
parallel tasks that should take 2 weeks, so one resource would spend 25% one
each task each day. I tried to level the tasks but it kept the resource at
100% for each task and made the tasks serial.
 
R

Rod Gill

Make the units for each assignment 25%. Select Window, Split to see the Task
Form and make it easy to edit assignments.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top