T
TecMan
I have a task that is a two day duration task. I have a resource that is
assigned 100% of the time to this project. I have another resource that is a
resource on the project and must particpate in the task but does not actively
contribute to the completion of the task. How do I manage these resources in
MS Project?
Because teh second resource is also responsible for other tasks, I am trying
to determine if the activities that (s)/he is responsible for becomes a
gating item for task start, task duration or task completion.
Any suggestions would be greatly appreciated.
assigned 100% of the time to this project. I have another resource that is a
resource on the project and must particpate in the task but does not actively
contribute to the completion of the task. How do I manage these resources in
MS Project?
Because teh second resource is also responsible for other tasks, I am trying
to determine if the activities that (s)/he is responsible for becomes a
gating item for task start, task duration or task completion.
Any suggestions would be greatly appreciated.