Hi minniebe,
My answers are embedded below:
Julie
minniebe said:
So to rebaseline a schedule I:
1. Clear my original baseline
[Julie] It is not necessary to clear the original baseline. If you
re-baseline, it will overwrite your original baseline. If you are
using
Project 2002 or 2003 and you want to preserve your original baseline,
you can copy the original baseline to another Baseline field (for
example Baseline1) using Tools > Tracking > Save Baseline, Save
interim
plan and copy Baseline into Baseline1.
2. Delete unnecessary tasks
[Julie] Yes.
[Julie] Yes.
4. Update old start and finish dates
[Julie] Not sure what you mean here. You should not be entering
start
and finish dates into Project. In a project plan scheduled from a
start
date (entered in Project > Project Information), entering a start
date
creates a Start No Earlier Than constraint and entering a finish date
creates a Finish No Earlier Than constraint. Where at all possible,
the
start and finish dates of your tasks should be calculated by MS
Project
based upon the Start Date of the Project, the working time as set in
the
project calendar, the duration of the tasks, the
predecessor/successors
(links) between tasks, and the calendar of the resources assigned.
5. Reestablish my links (predecessors)
[Julie] Yes.
[Julie] Correct.
Being new to project. I would appreciate step by step answers.
Thanks for all your help
[Julie] You're welcome and I hope this helps. Let us know how you
get
along.
Julie
:
minniebe wrote:
I have been tasked to re-baseline a project. Can someone
provide
me with an
overview of the steps necessary to do this?
I also will be deleting some tasks that have predecessors. Will
this create
a problem with the associated tasks and their dates?
Thanks for all your help!
I try to replace all links before I remove any tasks, just seems
easier
to figure them out then rather than after the tasks are gone.
Everything in the schedule, except possibly meetings, should be
linked
again when you're done. Then just do the same steps you did when
you
originally baselined. If you want to save the original baseline
before
you re-baseline, just go into the Baseline dialog box and copy the
current baseline into another set of Baseline data, then
re-baseline.
Hope this helps in your world.