how do I show task duration in months instead of days

S

SloveniaDave

Can I add text at the end of each task bar to show the total number of man
months, but still keeping the duration in days in the main 'duration' column?
 
J

Jan De Messemaeker

Yes.
Tools, Options, schedule, work is entered in months
Now through Bar Styles change the text at the right to Work
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
SloveniaDave said:
Can I add text at the end of each task bar to show the total number of man
months, but still keeping the duration in days in the main 'duration'
column?
 