How do I sort by date and Time

H

Harry

I want to sequence tasks by date and time in ascending order and create a
view of the project plan file. Any ideas to accomplish this easily. Thanks.

Harry
 
J

JulieS

Hi Harry,

Try Project > Sort > Sort by... and then select the date field you wish to
sort by. In the Sort dialog box you can also select ascending or
descending.

You may then copy the sorted view (View > More Views , select the current
view) and rename it. Return to the previous view, and re-sort that view by
ID. You can then quickly switch between the views to see the sorted view.

Hope this helps. Let us know how you get along.

Julie
 