Well step by step, try the following:
Insert a task...
Right click to enter 'task info'...
on 'Advanced' tab set 'Task Type' to 'Fixed Duration'...
Now introduce a split by right clicking the task bar in the Gantt, but
keep
an eye on the duration. You will notice the duration increases to
include
the split/non-work duration also.
Now repeat but set 'Task Type' to 'Fixed Units' et voila, the split is
introduced but the duration remains the same. Presumably as it now
includes
work effort as the measurable, as it should be (or at least how I
wanted
it).
It's a strange one for sure, I never encountered it before.
I hope this helps.
Andy.
:
That's funny, it doesn't do it on mine. I take a two week task and
split
it, introducing 1 week of down time in the middle. Now the total
elapsed
time on the task is three weeks but the duration column still reads "2
wks"
because the downtime in the middle doesn't count for duration. I mark
it
50% complete and the dark line runs through the first half. I mark it
60%
complete and the dark line runs just into the second half a skoshe and
shows
actual duration 6 days, remaining duration 4 days. Take us step by
step
exactly how you can recreate the problem if you can - I'm really
curiuous.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi Steve and John,
It is defintely the duration that I'm refering to against tasks (not
summaries). If I introduce a split into any individual task the
duration
increases to encapsulate the over time including the split portion
of
the
task. Furthermore, if I the increase the percentage complete it
calculates
based on the overall duration including the split. Given that this
duration
is incorrect, 50% for example is somewhere in the middle of the
split
and
not
clearly reference in the gantts prgress.
I agree that it is not a template issue as I wrote them. It would
appear
to
be a setting for project itself but I can't find it. I am new to
MSP
2003
but not to MSP itself which I have been using since 95 and most
recently
MSP2000.
Thanks for your responses,
Andy.
:
Are you sure you're notconfusing duration with elapsed time? A
split
will
increse the elapsed time between start and finish but not the
duration.
([Duration] = [Elapsed Time] - [Non-working Time])
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Steve,
Hi btw, I have the reverse problem with project 2003 by which I
mean
that
the split task increases the duration thus making the % complete
of
say
50%
somewhere in the split portion of the task bar. I am using a
template
some
maybe it's a setting that I need to change. Can you tell me how
to
change
this so that the duration does not increase when introducing a
split.
Kind regards,
AndyB
:
A task with 6 six hours of work spread out into 3 2-hour
segments
of
full-time work over 2 months is not a 2 month duration task. It
is
a
6
hour
duration task. The time between segments is "off the books"
just
as
if
the
task took a vacation and as far as duration is concerned it's
like
a
weekend, it doesn't exist.
Try it. Create a 2 week task. Using the "split task" tool on
the
toolbar,
click in the middle of the task and drag the second week out for
two
weeks
into the future. You should see a bar for the first week, a
dotted
line
for
two weeks, and a bar for the last week. Now look at the
duration
field.
It'll still say "2 weeks," not 4.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
I posted a question about splitting a task in MS Project
yesterday
on
an
MS
discussion page that came up from Help in MS Project.
I then noticed this posting.
I tried the instructions given by Mike Glen to split the task
and
also
went
the web site TechTrax and followed the instructions there
including
when
it
did not work.
When I go to adjust the ending date to 2 months for the 6 hour
task
it
moves
my start date to the last day of the 2 months.
I cannot split this task successfully. It is a 6 hour task
that I
wanted
to
split into 3 separate 2 hour segments.
I am the only resource for this project so I do not have any
resources
assigned.
I posted ÃfffÃf,Ã,¢?oSplit TaskÃfffÃf,Ã,¢?Ãff,Ãf,Ã, by
MrDRBC.
Any ideas?
Bill Perschke
:
Sorry, Levi, that referred to the TechTrax article - at the
end.
Mike Glen
Project MVP
Levi Page wrote:
Thanks so much. I will give that a try. How do I rate you?
This
is
the first I have used the Microsoft Online Discussion
Groups
and
I
don't see anywhere to specify a rating?
Thanks,
Levi
:
Hi Levi,
Welcome to this Microsoft Project newsgroup
From the Gantt Chart view, Window/Split, and in the lower
screen
change Fixed Duration to Fixed Work and then OK. Now
change
the
Work to 6h and OK now re-set the Duration to 2 months.
The
Units
should change to 2%. These techniques are explained for
multiple
resources (but obviously apply to a single resource) in my
series
on
Microsoft Project in the TechTrax ezine, particularly
#10 -
Multiple
Resource Assignments, at this site:
http://tinyurl.com/2xbhc
(Perhaps you'd care to rate it before leaving the site,

Thanks.)
FAQs, companion products and other useful Project
information
can
be
seen at this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
Levi Page wrote:
I have tasks such as Project Planning that will 6 hours,
but
the
six
hours will occur over a two month period. I want my
duration
to
reflect how long it will take me to do all tasks, but
since
I
am
specifying two months as a duration, it thinks i am
actually
performing two months worth of work instead of six hours
worth.
How
do I specify that a task will take x amount of hours over
a
certain
period of time? Currently I have to add an addiational
field
called
Task Hours, but this will not automatically adjust my
start
and
finish dates which is what I want. My email address is
(e-mail address removed)