How to adjust calendar in MSP 2003

M

MSP Beginner

I used MSP 2007 Professional in my personal computer and I get accustomed to
it.

But in my company, the version they use is MSP 2003 Standard and I got some
problem with the calendar adjustment. There is no button for me to adjust the
work week as I did with MSP 2007. MSP 2003 only allows some exception
adjustment on some days of the week, which makes a huge issue for me on the
duration. Our work week starts on Sunday and ends on Thursday. Friday and
Saturday are weekend.

If I cannot change the work week, I have to change the days one-by-one and
it is such a hassel. Is there a faster way to create new work week that
allows working from Sunday to Thursday?

Thanks everyone.
 
R

Rod Gill

Hi,

Yes, click and drag the S for Sunday thru to T for Thursday and edit the
days. Then do same for F for Friday and S for Saturday. This will change
every day in the calendar.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 