how to assign a resource (person) for a certain duration

M

Manoor

good day all
please help me in this
if i want to assign a resource (person or number of persons) like safty
officers> they cant be assigned for certain task but it is assigned for the
project period or for a certain period.
how to do this
thanks in advance

Mannor
 
J

John

Manoor said:
good day all
please help me in this
if i want to assign a resource (person or number of persons) like safty
officers> they cant be assigned for certain task but it is assigned for the
project period or for a certain period.
how to do this
thanks in advance

Mannor

Mannor,
I don't understand what you mean by, "...they can't be assigned for
certain task...".

Tasks are the activities in a project plan. Resources are the labor or
material to actually work or be used on those activities. Assignments
are the link between tasks and resources. Assignments cannot exist
without a task AND one or more resources. Given that, if you have
certain resources that support various tasks throughout the life of the
project, you will need to create a separate task for that support, or
assign them to each task individually along with other performing
resources. In the former, it is sometimes desirable to set up weekly or
monthly support tasks instead of one large task that covers the whole
length of the project. Doing so can make tracking and/or modification of
the plan, (if necessary), much easier.

In addition, there are various ways to modify individual resource work
time with respect to task start and finish dates. One is through
customized resource calendars. Another is by simply assigning the
resource by specific start and finish dates. Yet another is through
resource availability schedules.

Hope this helps.
John
Project MVP
 
M

Manoor

John said:
Mannor,
I don't understand what you mean by, "...they can't be assigned for
certain task...".

Tasks are the activities in a project plan. Resources are the labor or
material to actually work or be used on those activities. Assignments
are the link between tasks and resources. Assignments cannot exist
without a task AND one or more resources. Given that, if you have
certain resources that support various tasks throughout the life of the
project, you will need to create a separate task for that support, or
assign them to each task individually along with other performing
resources. In the former, it is sometimes desirable to set up weekly or
monthly support tasks instead of one large task that covers the whole
length of the project. Doing so can make tracking and/or modification of
the plan, (if necessary), much easier.

In addition, there are various ways to modify individual resource work
time with respect to task start and finish dates. One is through
customized resource calendars. Another is by simply assigning the
resource by specific start and finish dates. Yet another is through
resource availability schedules.

Hope this helps.
John
Project MVP

thanks alot john
i found that information v useful
i'm new with project
wt i meant that if there an empolyee he works for the project period
everyday regardles wt tasks are performed this day i.e safty officers,
administrations, secretary and so.
thanks again
 
J

John

Manoor said:
thanks alot john
i found that information v useful
i'm new with project
wt i meant that if there an empolyee he works for the project period
everyday regardles wt tasks are performed this day i.e safty officers,
administrations, secretary and so.
thanks again

Mannor,
You're welcome.
John
 